2022-04-06 Daily stand up
2022-04-06 Daily stand up
Date
Apr 6, 2022
Participants
Reckitt (RB):
Matt Lau
Robert RuszczykDataArt (DA):
Nikita Pushnyak
Julia Boyarshchikova
Sergey Kiselyov
Anton Merkulov
Nikita Puzyrenko
Goals
DA to tell about current progress, restrictions and next steps
RB to clarify remaining issues
Agree on first MVP steps implementation
Action items
DA to provide updated estimates and budget after technical discussion and scope review @Sergey Kiselyov (Unlicensed)Nikita.Pyshnyak@dataart.com
RB to confirm the scope officially (review in the confluence, what is necessary and what is not) @nathan.mckean@reckitt.com (Unlicensed) @Matt.Lau@reckitt.com@Golebiewska, Aga (Unlicensed)
RB & Ekino to provide the link to updated Design inputs (Figma files) @nathan.mckean@reckitt.com (Unlicensed)
DA schedule the demo sessions every week (once development is started) @Sergey Kiselyov (Unlicensed)
Key takeaways
- Master vs develop approach issue was discussed on tech meeting. Testing approaches were discussed as well. Preliminary ways of working are agreed
- Demo session was provided by Ekino. Updated design inputs will be provided and investigated by DA team
- Hero promo development & testing will take 4 weeks as per submitted timeline. DA team should start asap
- Budget issue is planned to be resolved after updated Figma files receipt