\uD83D\uDDD3Date

\uD83D\uDC65Participants

  • Reckitt (RB):
    Matt Lau
    Robert Ruszczyk

  • DataArt (DA):

Nikita Pushnyak
Julia Boyarshchikova
Sergey Kiselyov
Anton Merkulov
Nikita Puzyrenko

\uD83E\uDD45Goals

  • DA to tell about current progress, restrictions and next steps

  • RB to clarify remaining issues

  • Agree on first MVP steps implementation

✅Action items

⤴Key takeaways

  • Master vs develop approach issue was discussed on tech meeting. Testing approaches were discussed as well. Preliminary ways of working are agreed
  • Demo session was provided by Ekino. Updated design inputs will be provided and investigated by DA team
  • Hero promo development & testing will take 4 weeks as per submitted timeline. DA team should start asap
  • Budget issue is planned to be resolved after updated Figma files receipt